Tasks are how a project moves
A project is made of tasks, grouped under the phases of your pipeline: "Dig", "Steel", "Gunite", "Plumbing inspection", "Plaster". Each task has the people on it, planned dates (days, not appointment times), actual dates and a status (Open, In progress, Done). A project type is a ready-made task list you set up once and reuse, so a new pool build gets its 70 tasks in one click. This needs Projects turned on for your company (see Projects overview).
Set up a project type
Open Project setup (the button on the Projects page, or Services → Project setup in the sidebar) and stay on the Project types tab. Click New project type.
- 1Give it a name, like New pool build or Replaster.
- 2Under each phase, type a task and press Enter to add the next one, or click Add task. To fill it fast, paste your task list from a spreadsheet or document: one task per line.
- 3For each task, optionally set Days (a whole number from 1 to 365) and After, the task it waits for (only a task above it). With both, every project made from the type gets planned dates worked out for it.
- 4Optionally mark a task as a payment step (the Payment column) or give it messages to send when it starts or is done. See payments and task messages.
- 5Click Save project type.
- A project type can have up to 250 tasks. Split a bigger build into two types.
- The ⋯ menu on a type: Edit, Duplicate (a copy to rename and change), and Archive or Restore. An archived type can no longer start new projects; projects already made from it keep their tasks.
- Editing a type later does not change projects already made from it. Each project has its own copy of the tasks.
- Changing project types is for whoever manages project setup (Owner and Administrator by default). Anyone who can see projects can open a type to look at it.
Add tasks to a project
- From a type when you create the project: pick the Project type on the New project form, or on the quote that starts the project. Its tasks are copied in with planned dates from the start date (or today).
- From a type later: on the Tasks tab, click Add tasks from a project type (on an empty project it is a button; otherwise it is in the ⋯ menu, More task actions). Pick the type and Plan dates from. On a project that already has tasks, the type's tasks are added after the ones in each phase; nothing is replaced.
- By typing: under a phase, type in Add a task to (phase), or paste a list and press Enter. Paste several lines to add one task per line.
Click a task to open Edit task: Task (its name), Phase, Status, Assigned to, Comes after (or "Nothing (starts on its own)"), the planned Start, Days and End (a start and a number of days work out the end), the actual Started and Ended (filled in for you when the task is started and finished), and its Messages. Click Save task. Delete needs a confirm, because it can't be undone.
- Change a task's status from its status pill in the list, or tick it to mark it done. Starting a task fills its started date; finishing it fills the ended date with today.
- Assign phase on a phase header puts the same people on every open task in that phase.
- Drag tasks to put them in a new order or move them to another phase (with the All filter on and done tasks showing).
- Changing one task's dates does not move later tasks. Use Re-plan dates for that (below).
- A task is past due when its planned end has passed and it is not done; past due dates show in red.
List, Gantt and Calendar
The Tasks tab has three views: List, Gantt and Calendar. The same filters work in all three: All, Open, Mine (tasks assigned to you) and Past due, plus the Hide done switch.
- List: tasks under each phase with the team, the Planned Start, End and Days, and the Actual Started, Ended and Days.
- Gantt: a bar per task from its planned start to its planned end, grouped by phase, on a Days or Weeks scale. Tasks in progress and actual dates that are off plan are marked. Click a bar to open the task.
- Calendar: a month at a time with the tasks on their days, and Previous month / Next month arrows.
The Gantt is read-only: you cannot drag bars to change dates. Change a task's dates in the task itself, or with Fill in dates and Re-plan dates.
Fill in dates and Re-plan dates
Tasks with no dates do not show on the Gantt or the calendar. Two tools fix the dates for you:
- Fill in dates (in the ⋯ menu, and on the Gantt and calendar when tasks have no dates): each task with no dates gets 1 day, one after another, from the job's start date (or today when the job has none). Tasks that already have dates keep them. The toast says how many were dated and has Undo.
- Re-plan dates (shown when tasks have a number of days): works out the planned start and end again for every task with a number of days, from the job's start date, each starting the day after the task it comes after. You confirm first, because planned dates you changed by hand on those tasks are replaced. Tasks with no number of days, and actual dates, stay as they are.
Moving through phases
- When the last open task of the project's current phase is done, the project moves on by itself to the next phase that still has open tasks. The toast says so ("Moved to 3 · Permit: all Pre Build tasks are done.") and has Undo. It never moves a project backwards: reopening a task leaves it where it is.
- Move it yourself with the phase bar on the project page (Move to the next phase, or the menu Move this job to), by dragging its card on the pipeline board, or with Move to phase in its ⋯ menu.
- The phase and the project status are separate: finishing tasks does not set the status to Completed. See project statuses.
Who can do what
- Adding, editing, deleting and moving tasks, assigning people and filling in dates is for anyone who can edit projects (Owner, Administrator and Office Manager by default).
- A technician can start and finish the tasks assigned to them, from the project page or the technician app (see project tasks in the app). Any employee can be put on a task; the project's Crew (on the Details tab) lists only employees who can be assigned field work.
- Project types are for whoever manages project setup. Phases are changed by anyone who can edit projects.
Frequently asked questions
Is there a Gantt chart for projects?
Yes. On a project's Tasks tab, pick Gantt. It draws each task from its planned start to its planned end, by phase, on a Days or Weeks scale. It is read-only: change dates in the task.
Can I drag tasks on the Gantt to reschedule them?
No. The Gantt is read-only. Open the task (click its bar) and change its dates, or use Fill in dates or Re-plan dates on the Tasks tab.
If I change a project type, do my existing projects change?
No. A project gets its own copy of the type's tasks when it is made. Editing the type changes only projects made from it afterwards. To add the type's tasks to an existing project, use Add tasks from a project type on its Tasks tab.
Do project tasks go on a technician's route?
No. A project task is not a route stop. The people on a task see it in My project tasks in the technician app.